Sunday, 19 November 2023

Scalefour Cumberland 23 (SolRail 23)

My demonstration table at Scalefour Cumberland 23 (SolRail 23)

We all tackle planning a layout differently so felt worried about sitting behind a table titled "Planning a Layout in P4". Why should my way be any better than the next persons?

Well, I shouldn't have worried. A number of people stopped, even sat down and to ask questions. All seemed interested in both projects on display. Obviously, some thought what I'd produced was OTT, but most kindly gave positive feedback along with asking when they might see the layouts.

On the other side of the coin, I also learnt much from fellow demonstrators and modellers within the room. So this weekend has been an extremely interesting and enjoyable experience.

Monday, 30 October 2023

A Temporary work area and SolRail 23

I'm still waiting for power to be installed in the Log Cabin. The house rewiring took longer than expected, and we decided to postpone connecting the log cabin until other outside work is completed in order to finally get the interior signed off.

In the meantime, I've recently negotiated a small area in the snug at which I can work on a few projects. I'll have to see if the better half will allow me to solder, but for the moment I've been working on the 1/8th scale model of my proposed Boscarne Junction.

I'd planned to make this scale model mainly to help with thoughts on baseboard construction and to see how it will look visually. As I've been cajoled into setting up a table titled 'Planning a new layout, Boscarne Junction' at Scalefour Cumberland 23, it will come in very handy. Unfortunately, as I've been distracted by entering the Scalefour Jubilee Challenge, I'll still be building the model.


There will be another 1/8th scale model of my Jubilee Challenge project on the table to discuss with those that might be interested.

Thursday, 28 September 2023

Calculating possible weight for the baseboards

I wanted to calculate the weight of my baseboards using insulation and plywood. This was after reading about the weight of another modeller's baseboards made totalling from plywood.

Googling the weight of different thicknesses of plywood, I came up with the following rough calculations for one of the 5ft x 2 ft boards.

  • The top of 3mm plywood & insulation - 2.1kg
  • The 2 ends of 9mm play (1kg each) -2kg
  • The front Facia - 0.3kg
  • Back screen (inc. insulation at bottom) - 1.6kg
  • Internal sections of insulation - 0.5kg
  • Track approximately - 0.5kg

So my best guess at the weight of one of the 5ft x 2ft baseboards without scenery, track etc. will be approximately 7kg (15.5lbs). I've tried to make an allowance in the figures for glue and baseboard dowels. So the 5ft x 2ft baseboards might only weigh the equivalent of 7 bags of sugar or a little more. Size wise still too cumbersome for one person to carry but two people should easily be able to manhandle them. 

One problem rearing its head is the size or rather shape of the final scenic baseboard at the Bodmin, Wenford bridge end of the layout. Question being will it go through a standard door width in the configuration I'm planning? The creation of an 8th scale model of the layout should help me answer this question.

Wednesday, 28 June 2023

Thoughts on Baseboard Construction

I have mumbled a little, on a couple of blogs, about my thoughts for baseboard construction. The baseboards for Boscarne Junction are going to be relatively large. If I used the plywood and softwood sandwich technique they’d require two people to move them. The basic idea is to build baseboards that I’ll be able to lift and move around when I’m in my 7th decade.

When visiting York Model Railway show in 2019 I became intrigued with Gordon Gravett’s baseboards for Arran Quay and way he’d sandwiched insulation board between thin plywood. I was not sure about using the same insulation board for the baseboard tops but he had made it work. This method of construction must have created a very light baseboard easy to lift and move/transport.

Many years ago I purchased a number of 2ft x 4ft x 1 inch sheets of insulation board for creating hex terrain for wargaming. There are still eleven sheets left from that project which are taking up space in my shed. My intention is to rather than dispose of these sheets is to make good use of them for Boscarne Junction’s baseboards.

As my insulation board is only 1 inch thick I’ll not be follow Gordon’s methods fully but to borrow his general idea. Hopefully the drawings below will help to explain my intentions better than words.



Sunday, 25 June 2023

Version 9

Just when I thought version 8 was the final track plan, I’ve now produced a version 9.

When starting to consider how the layout was going to be operated, my thoughts went to the enjoyment I gained when invited to operate other layouts. Especially those where a signalman controls a signal box and the train driver has to obey the signals. The use of bell codes, interlocking lever frames, and train driving to signals fascinated me. It all added to the operating experience and is something I'd like to pursue for Boscarne Junction.I questioned how I going to include this feature into my model?

If I'm going to create off scene signal boxes in the Fiddle Yards, which use bell codes to communicate with Boscarne Junction signal box, I have a problem with the Wenford branch. There was no signal box at Dunmere or on the Wenford branch. I believe the Guard of the Wenford train walked to Boscarne signal box to retrieve/return the key for the Dunmere Ground Frame. Then the train crew operated the two ground frames. I thought this is something I’d like to include in the model.

In an attempt to include this type of operation, I’ve decided to separate the layout into three operating areas

  1. Boscarne Signal box & Wadebridge Fiddle Yard (There would be the possibility to split Wadebridge Fiddle Yard away from the Boscarne Box).
  2. The Bodmin North, Bodmin General & Wenford Fiddle Yard.
  3. Train Driver who’ll also control both Boscarne and Dunmere ground frames as the train crew would have done.

In doing the above, should give a reasonably authentic operating experience to this layout.

At this point I’d like to thank David Woodcock again. I’ve only been able to consider doing this due to his contribution with the signal diagrams and locking tables. Many thanks David.

I started mess around with the plan to see if I could squeeze in Dunmere Ground Frame and the junction turnout into the track plan. The only way I found was to move the whole of version 8 track plan back to the left. This dramatically reduced the scenic area before the level crossing which I’d created in version 8. I felt this compromise for home use was well worth taking as it will increase operational interest. There were always thoughts with version 8 I’d add a further scenic board at the Wadebridge end for exhibitions, version 9 will be no different. Still a bit left to do as there are still a few scenic items to identify and mark on the plan along with checking on edge profiles and land contours.

 

Above is how the layout will look when at home. I briefly mentioned that the track plan is now drawn to fit the baseboards. This is due to the comment about knowing angles for baseboard construction. I will construct the three baseboards making the curved scenic section with the same diverging angle (23 degrees). They will either be stackable on each other when boxed or I should be able to construct a rack into which they will all slide.

Below is my cursory thoughts for exhibitions.



Saturday, 17 June 2023

Further thoughts on the track plan (v.8)

 I wasn’t going to revisit the track plan until the man cave was empty so its internal dimensions could be confirmed. That was until I was able to squeeze in a day’s visit to Boscarne Junction after being in Torquay for a wedding. The visit was to take photos of the wider surrounding area. The site is now dramatically over grown compared to the photographs I have which were taken in the early 1960s. That said the embankments, paths, field boundaries seem to not have altered. Plenty of photographs were taken which I hope will enable me to replicate the topography around the junction.

While at Boscarne then subsequently looking at my track plan I began to feel I’d drawn it a little out of proportion. Siding 2 (along the back towards Bodmin North) looked too long. In reducing its length  has made it feel more in proportion. In doing so I’ve been able to move the whole track plan to the right a little which has slightly increased the visible track left to the level crossing.  In my attempt to balance the space available between scenic and fiddle yards I’ve had to reduce the overall length of the junction and sidings. There is approximately 13.5ft between the two quarter mile posts as opposed to 17.3ft for a scale quarter mile. Even so, the hope is this will still create a recognisable layout with the ability to operate as near as possible realistic train movements to a replica BR timetable.

Boscarne Junction v.8

To give me the possibility to add a further board at the Wadebridge end I’ve also twisted the track plan slightly. In doing so means the track beyond the level crossing (towards Wadebridge) now runs parallel to the baseboards sides. This will allow the fiddle board that I’ll be using at home to be connected to the extra scenic baseboard if it ever is invited to a show.

Next thoughts:

  1. How to build the baseboard supports and at what height should the layout be?
  2. How to integrate lighting on the model as well as prevent other external lighting to affect the visual effect. 
  3. Need to think about the overall operation of the layout (my initial thought may need to produce v.9 of the track plan)

Tuesday, 28 February 2023

Could I have planned the layout better?

The new "Man Cave" is an extended Dunster log cabin and in part of its construction there are two walls that protrude into the internal space of the room.

Initially I was thinking about turning Rospeath Lane into a "roundy roundy" but these two walls hindered this to some degree. Many plans were drawn but I began to realise that it would become a very ambitious layout. One that may require more time than I have left to bring to a reasonable state of completion. Also I started to have thoughts about how I was going to continue with exhibiting a layout along with improving and learning more about the hobby. That the main reason why Boscarne Junction has been born.

So could I have designed it any better?


I've tried a few different ways of fitting the plan into the space but didn't want to compromise too much on the track plan. My main though was to keep the integrity of the track layout with the only compromise being taken on the siding length. The result being the track plan below.



After posting my thoughts and ideas on a couple of forums I received a good few replies with excellent suggestions. The major problem I had with the track plan above was transferring cassettes between Bodmin North/Wenford and the Bodmin General cassette boards. One suggestion was to curve the Bodmin North line so that the Bodmin North/Wenford and Bodmin General cassette boards could be combined.


I was not sure about curving the Bodmin North line as I felt it would deviate too much from the original and therefore loose some of the genuine feel of the junction. Even so, I played around a little and finished up with the plan below.



I must admit it solves the problem very well with transferring full and empty clay wagons between the Bodmin North/Wenford and Bodmin General Lines. The other bonuses this plan gives are; 
  • It will allow me to include the Southern Railway bridge over the River Camel. 
  • With enough trees this compromise of curving the Bodmin North line could be masked quite well.
  • The trees will also be a natural break between the bridge and junction to give a tantalising glimpse of trains running over the bridge to/from Boscarne to Bodmin North/Wenford before they appear at the junction or disappear into the cassette board.
  • By extending the Bodmin North line will allow any shunting of Siding 2 from this end to be contained within the scenic section of the layout.

As this curve brings the two lines closer together I need to work out the land contours leading up to the Southern Railway Bridge. Also the new baseboard is going to complicate storage and transportation. 


One of the many decisions I need to make is whether to include a track around the back of the layout.  This would be used to exchange clay wagons between the Wadebridge and Bodmin cassette boards rather than carry a cassette the length of the layout. I need to discover how regular clay traffic travelled via Wadebridge and along the North Cornwall Line. Then decide if this is a movement I'd include in the timetable.